Scheduling & Earned Value

6 min read


  • Forward pass: ES of an activity = largest EF of its predecessors; EF=ES+duration\text{EF} = \text{ES} + \text{duration}.
  • Backward pass: LF = smallest LS of its successors; LS=LF−duration\text{LS} = \text{LF} - \text{duration}.
  • Total float=LS−ES\text{Total float} = \text{LS} - \text{ES}. The critical path is the chain with zero total float, and it is the longest path through the network.

Worked: a status report

BAC = $500k, PV = $200k, EV = $180k, AC = $210k. CV = −$30k, SV = −$20k, CPI=0.86\text{CPI} = 0.86, SPI=0.90\text{SPI} = 0.90: over budget and behind schedule. EAC=500/0.857\text{EAC} = 500/0.857 = $583k.