Estimating & Productivity

6 min read


Worked

  • 10,000 BCY at 25% swell is 12,500 LCY; with 15 LCY trucks that is 834 loads.
  • A loader with a 4 LCY bucket on a 0.6 minute cycle, working 50 minutes an hour: 4 × 50/0.6 = 333 LCY/h.