Determinacy, Loads & Load Paths

6 min read


Worked: a factored floor load

A beam picks up a 10 ft tributary width of floor carrying 80 psf dead and 50 psf live. D=0.8D = 0.8 kip/ft and L=0.5L = 0.5 kip/ft. 1.2D+1.6L=0.96+0.80=1.761.2D + 1.6L = 0.96 + 0.80 = 1.76 kip/ft, which governs over 1.4D=1.121.4D = 1.12 kip/ft.