Swell and Shrinkage
The change in volume of soil between its natural (bank), excavated (loose) and compacted states.
Soil excavated from the ground bulks up: loose volume = bank volume × (1 + swell). Compacted into a fill, it ends up denser than in the bank: compacted volume = bank volume × (1 − shrinkage). Common earth swells by roughly 20% to 30%.
Hauling is counted in loose cubic yards, because that is what fills a truck, while excavation is usually paid in bank cubic yards and embankment in compacted yards. Mixing the three states is the commonest error in earthwork estimates.
How much of the FE Civil exam is Construction Engineering?
Worked example
A footing excavation removes 1,200 bank cubic yards (BCY) of soil with a swell of 25%. Trucks carry 12 loose cubic yards (LCY) each. How many truck loads are needed?
- Loose volume: LCY = BCY × (1 + swell) = 1,200 × 1.25 = 1,500 LCY.
- Loads: 1,500/12 = 125.0 → 125 loads (round up: a part load is still a trip).